OPTIONS W7w/e/c |
||||||
Taking all factors into account the preferred option was option W7 - a full four track scheme which after further consideration became option W7X. Three
variations of option W7X were developed as follows:-
|
Environmental Studies | Having assed the pros and cons of each
option in detail, Ove Arup were then asked to give further consideration /
development to the W7 option.
Major environmental constraints were identified during this process and are detailed by maps 1A and 1B In addition to the environmental constraints, a
number of other factors had to be taken into consideration
|
||||||||||||||||||||||||||
Constraints |
The route was divided into seven geographical sections and a
preference was established in each section. There were three areas
where the preferences were stronger.
Unfortunately no single scheme could satisfy all
these constraints. |
||||||||||||||||||||||||||
The decision making process |
Taking all of the constraints into account, the first option considered was Option W7C and the following factors were critical:
Options
W7W and W7E were then compared:
As a result of this comparison Option W7E was the preferred solution despite being more costly. We believe that the preferred option offers the- best overall balance between the many competing interests. |
||||||||||||||||||||||||||
So what happens next? |
Over the next 18 months we will undertake:
We will prepare detailed plans that will show the exact
effect on property and land and this work will lead to :
We believe there will almost certainly be a need for a
Public Inquiry, which is likely to take place in about Spring/Summer 2002.
Having considered the Inquiry Inspector’s Report, the Secretary of State
for the Environment, Transport and the Regions will decide whether to
authorize the scheme
|